| Assessment Year | 2006 |
|---|---|
| Principal Product | Hardwood lumber |
| NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
126,600
ft2
|
| Annual Production | 7,500
thousand feet
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $245,887 | 2,966,641 |
kWh
|
$0.083 |
| Electricity Demand | $104,547 | 7,620 |
kW-mo/yr
|
$13.72 |
| Natural Gas | $55,411 | 2,719 |
MMBtu
|
$20.38 |
| Wood | $3,710 | 1,559 |
MMBtu
|
$2.38 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,180 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,308 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $32,853 | $158,280 |
$23,998
297,000
kWh
|
$8,855
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,311 | $27,000 |
$6,230
77,100
kWh
|
$3,081
-
kW-mo/yr
|
- | |
| 03 | 2.4323: Use optimum size and capacity equipment | $5,019 | $8,507 |
$2,521
31,200
kWh
|
$2,498
-
kW-mo/yr
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $935 | - |
$630
7,800
kWh
|
$305
-
kW-mo/yr
|
- | |
| 05 | 2.2511: Insulate bare equipment | $62 | $150 | - | - |
$62
-
MMBtu
|
|
| TOTAL RECOMMENDED | $48,180 | $193,937 |
$33,379
413,100
kWh
|
$14,739
-
kW-mo/yr
|
$62
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,308 | $27,150 |
$6,860
84,900
kWh
|
$3,386
-
kW-mo/yr
|
$62
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs