| Assessment Year | 2005 |
|---|---|
| Principal Product | Laminated barrier fabric |
| NAICS | 313320: Fabric Coating Mills |
| SIC | 2295: Coated Fabrics, Not Rubberized |
| Sales Range | $10 M to 50M |
| # of Employees | 51 |
| Plant Area |
50,950
ft2
|
| Annual Production | 9,000
thousand feet
|
| Production Hrs. Annual | 5,620
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $193,205 | 2,460,000 |
kWh
|
$0.079 |
| Electricity Demand | $35,399 | 7,764 |
kW-mo/yr
|
$4.56 |
| Electricity Fees | $1,077 | - |
|
- |
| Natural Gas | $251,654 | 34,632 |
MMBtu
|
$7.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $176,206 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $75,545 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $97,224 | $319,500 | - | - |
$97,224
-
MMBtu
|
|
| 02 | 2.2437: Recover waste heat from equipment | $46,372 | $49,355 |
$(-2,693.0)
(-31,400)
kWh
|
- |
$49,065
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,977 | $25,856 |
$14,977
172,600
kWh
|
- | - | |
| 04 | 2.2212: Use minimum safe oven ventilation | $7,370 | $1,900 | - | - |
$7,370
-
MMBtu
|
|
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,826 | $29,170 |
$8,109
94,400
kWh
|
$1,374
-
kW-mo/yr
|
$(-2,657.0)
-
MMBtu
|
|
| 06 | 2.7243: Improve air circulation with destratification fans / other methods | $2,702 | $1,962 |
$(-232.0)
(-2,700)
kWh
|
$(-29.0)
-
kW-mo/yr
|
$2,963
-
MMBtu
|
|
| 07 | 2.3212: Optimize plant power factor | $735 | $1,450 | - |
$735
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $176,206 | $429,193 |
$20,161
232,900
kWh
|
$2,080
-
kW-mo/yr
|
$153,965
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $75,545 | $106,281 |
$20,393
235,600
kWh
|
$1,374
-
kW-mo/yr
|
$53,778
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs