Assessment Year | 2004 |
---|---|
Principal Product | Thermal coatings |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
30,000
ft2
|
Annual Production | 108,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $154,866 | 2,081,800 |
kWh
|
$0.074 |
Electricity Demand | $44,481 | 8,630 |
kW-mo/yr
|
$5.15 |
Electricity Fees | $84 | - |
|
- |
Natural Gas | $24,790 | 2,350 |
MMBtu
|
$10.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,700 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,016 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $22,961 | $139,400 |
$20,118
256,600
kWh
|
$2,843
-
kW-mo/yr
|
- | |
02 | 2.2437: Recover waste heat from equipment | $10,584 | $2,465 | - | - |
$10,584
-
MMBtu
|
|
03 | 2.7224: Reduce space conditioning during non-working hours | $3,445 | $650 | - | - |
$3,445
-
MMBtu
|
|
04 | 2.7311: Ventilation system to shut off when room is not in use | $2,903 | - |
$1,521
19,400
kWh
|
- |
$1,382
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,626 | $250 |
$2,626
33,500
kWh
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $820 | $1,640 |
$820
17,100
kWh
|
- | - | |
07 | 2.7135: Install occupancy sensors | $361 | $512 |
$361
4,200
kWh
|
- | - | |
TOTAL RECOMMENDED | $43,700 | $144,917 |
$25,446
330,800
kWh
|
$2,843
-
kW-mo/yr
|
$15,411
-
MMBtu
|
||
TOTAL IMPLEMENTED | $17,016 | $3,877 |
$2,987
37,700
kWh
|
- |
$14,029
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs