ITAC Assessment: MA0520
ITAC logo
ITAC Assessment: MA0520
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Commercial Printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $5
M
to 10
M
# of Employees 35
Plant Area 25,000
ft2
Annual Production 1,400,000
lb
Production Hrs. Annual 4,420
hrs
Location (State) Vermont

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,221 527,428
kWh
Electricity Demand $39,788 2,640
kW-mo/yr
Electricity Fees $1,080 -
LPG $8,033 823
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,733 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,595

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings One-time Revenue or Avoided Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,609 - - - $2,609
02 2.2711: Utilize outside air instead of conditioned air for drying $2,161 $2,000 $337
5,274
kWh
$1,824
-
MMBtu
-
03 2.7224: Reduce space conditioning during non-working hours $1,389 $500 $461
4,688
kWh
$928
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $627 $4,496 $627
9,401
kWh
- -
05 2.7124: Make a practice of turning off lights when not needed $796 $800 $796
11,028
kWh
- -
06 2.6218: Turn off equipment when not in use $106 - $106
1,653
kWh
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $45 - $45
659
kWh
- -
TOTAL RECOMMENDED $7,733 $7,796 $2,372
32,703
kWh
$2,752
-
MMBtu
$2,609
TOTAL IMPLEMENTED $3,595 $2,500 $843
10,621
kWh
$2,752
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs