ITAC Assessment: MA0501
ITAC logo
ITAC Assessment: MA0501
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Newspaper and printed material
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 124
Plant Area 87,500
ft2
Annual Production 6,188
ton
Production Hrs. Annual 7,852
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $171,855 2,048,400
kWh
Electricity Demand $51,954 7,222
kW-mo/yr
Electricity Fees $3,837 -
Natural Gas $15,979 1,617
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,103 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,884

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $11,983 $6,000 - $11,983
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $9,653 $46,540 $8,551
109,630
kWh
$1,102
-
kW-mo/yr
03 2.3212: Optimize plant power factor $5,838 $9,990 - $5,838
-
kW-mo/yr
04 2.7135: Install occupancy sensors $4,410 $2,500 $4,410
56,534
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,219 $2,162 $2,219
27,673
kWh
-
06 2.7135: Install occupancy sensors $736 $300 $736
9,404
kWh
-
07 2.4239: Eliminate or reduce compressed air usage $264 - $264
3,375
kWh
-
TOTAL RECOMMENDED $35,103 $67,492 $16,180
206,616
kWh
$18,923
-
kW-mo/yr
TOTAL IMPLEMENTED $32,884 $65,330 $13,961
178,943
kWh
$18,923
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs