Assessment Year | 2001 |
---|---|
Principal Product | Stainless steel and high alloy castings |
NAICS |
n/a
|
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
110,000
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $658,691 | 9,355,508 |
kWh
|
$0.070 |
Electricity Fees | $600 | - |
|
- |
Natural Gas | $151,468 | 36,456 |
MMBtu
|
$4.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $56,351 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $35,844 | $60,000 |
$35,844
512,054
kWh
|
- | |
02 | 2.6218: Turn off equipment when not in use | $10,867 | - |
$10,867
155,250
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,790 | $35,000 |
$7,790
111,285
kWh
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,980 | - |
$3,980
56,848
kWh
|
- | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,300 | $13,000 |
$4,364
62,352
kWh
|
$(-1,064.0)
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,132 | $25,540 |
$2,132
30,445
kWh
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $808 | $2,000 |
$808
11,541
kWh
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $228 | $45 |
$228
3,264
kWh
|
- | |
TOTAL RECOMMENDED | $64,949 | $135,585 |
$66,013
943,039
kWh
|
$(-1,064.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $56,351 | $98,585 |
$57,415
820,213
kWh
|
$(-1,064.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs