| Assessment Year | 2001 |
|---|---|
| Principal Product | Roofing fasteners |
| NAICS |
n/a
|
| SIC | 3451: Screw Machine Products |
| Sales Range | $50 M to 100M |
| # of Employees | 230 |
| Plant Area |
76,000
ft2
|
| Annual Production | 1,000,000,000
pieces
|
| Production Hrs. Annual | 7,500
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $238,882 | 4,034,880 |
kWh
|
$0.059 |
| Electricity Demand | $97,295 | 8,824 |
kW-mo/yr
|
$11.03 |
| Electricity Fees | $27,589 | - |
|
- |
| Natural Gas | $90,242 | 11,523 |
MMBtu
|
$7.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $36,240 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,280 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.3131: Use evaporation to concentrate material | $23,000 | $10,000 | - | - |
$(-2,500.0)
-
MMBtu
|
$25,500
-
gal
|
|
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $5,800 | $360 |
$4,300
72,000
kWh
|
$1,500
-
kW-mo/yr
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,800 | $15,000 |
$4,800
79,700
kWh
|
- | - | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,160 | $12,000 |
$2,800
46,900
kWh
|
$960
-
kW-mo/yr
|
$(-1,600.0)
-
MMBtu
|
- | |
| 05 | 2.7135: Install occupancy sensors | $480 | $200 |
$480
8,100
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $36,240 | $37,560 |
$12,380
206,700
kWh
|
$2,460
-
kW-mo/yr
|
$(-4,100.0)
-
MMBtu
|
$25,500
-
gal
|
||
| TOTAL IMPLEMENTED | $6,280 | $560 |
$4,780
80,100
kWh
|
$1,500
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs