| Assessment Year | 2001 |
|---|---|
| Principal Product | Barbecue Ribs |
| NAICS |
n/a
|
| SIC | 2011: Meat Packing Plants |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
35,000
ft2
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 51,000
hrs
|
| Location (State) | Vermont |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $99,635 | 1,564,280 |
kWh
|
$0.064 |
| Electricity Demand | $39,009 | 3,336 |
kW-mo/yr
|
$11.69 |
| Electricity Fees | $4,083 | - |
|
- |
| Natural Gas | $54,284 | 9,991 |
MMBtu
|
$5.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,990 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,310 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.3131: Use evaporation to concentrate material | $20,600 | $10,000 | - |
$(-34,400.0)
-
MMBtu
|
$55,000
-
gal
|
|
| 02 | 2.2514: Cover open tanks | $2,300 | - | - |
$2,300
-
MMBtu
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $800 | $100 |
$800
11,700
kWh
|
- | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $500 | $150 | - |
$500
-
MMBtu
|
- | |
| 05 | 2.7135: Install occupancy sensors | $410 | $85 |
$410
6,152
kWh
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $380 | $600 |
$380
5,700
kWh
|
- | - | |
| TOTAL RECOMMENDED | $24,990 | $10,935 |
$1,590
23,552
kWh
|
$(-31,600.0)
-
MMBtu
|
$55,000
-
gal
|
||
| TOTAL IMPLEMENTED | $22,310 | $10,335 |
$1,210
17,852
kWh
|
$(-33,900.0)
-
MMBtu
|
$55,000
-
gal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs