ITAC Assessment: MA0480
ITAC logo
ITAC Assessment: MA0480
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product bearings
NAICS
n/a
SIC 3562: Ball and Roller Bearings
Sales Range $10
M
to 50
M
# of Employees 379
Plant Area 555,000
ft2
Annual Production 1,930,500
pieces
Production Hrs. Annual 7,020
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,229,145 24,974,209
kWh
Electricity Demand $467,357 51,665
kW-mo/yr
Electricity Fees $25,554 -
Natural Gas $248,068 55,497
MMBtu
Fuel Oil #6 $186,876 56,990
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $130,715 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,825

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Water Consumption Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $63,120 $282,000 $81,470
1,638,335
kWh
$21,150
-
kW-mo/yr
$(-39,500.0)
-
MMBtu
- -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,190 $10,000 $1,680
35,170
kWh
- - $(-490.0)
-
MMBtu
-
03 3.4114: Replace city water with recycled water via cooling tower $4,330 $8,000 $(-70.0)
(-1,465)
kWh
- - - $4,400
-
Tgal
04 2.7229: Air condition only space necessary $10,600 $5,000 - - - $10,600
-
MMBtu
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,290 $9,000 $1,290
26,964
kWh
- - - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,290 $6,500 $1,290
25,791
kWh
- - - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $21,450 $27,000 $21,450
448,417
kWh
- - - -
08 2.2625: Chill water to the highest temperature possible $8,620 $2,000 $8,620
177,022
kWh
- - - -
09 2.2623: Minimize condenser cooling water temperature $930 - $930
19,050
kWh
- - - -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,660 $5,000 $3,680
75,615
kWh
$980
-
kW-mo/yr
- - -
11 2.4231: Reduce the pressure of compressed air to the minimum required $1,020 - $1,020
20,516
kWh
- - - -
12 2.7135: Install occupancy sensors $12,215 $1,000 $12,215
247,655
kWh
- - - -
TOTAL RECOMMENDED $130,715 $355,500 $133,575
2,713,070
kWh
$22,130
-
kW-mo/yr
$(-39,500.0)
-
MMBtu
$10,110
-
MMBtu
$4,400
-
Tgal
TOTAL IMPLEMENTED $63,825 $48,000 $47,845
986,810
kWh
$980
-
kW-mo/yr
- $10,600
-
MMBtu
$4,400
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs