| Assessment Year | 2000 |
|---|---|
| Principal Product | Rubber belting |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 172 |
| Plant Area |
200,000
ft2
|
| Annual Production | 10,000,000
lb
|
| Production Hrs. Annual | 6,420
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $318,052 | 8,160,024 |
kWh
|
$0.039 |
| Electricity Demand | $255,923 | 23,038 |
kW-mo/yr
|
$11.11 |
| Electricity Fees | $21,927 | - |
|
- |
| Natural Gas | $426,474 | 92,552 |
MMBtu
|
$4.61 |
| Fuel Oil #4 | $33,716 | 6,153 |
MMBtu
|
$5.48 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,465 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,752 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7314: Reduce ventilation air | $9,400 | - |
$9,400
239,156
kWh
|
- | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,991 | $10,000 |
$5,845
114,596
kWh
|
$3,146
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $4,166 | $2,000 |
$4,166
86,460
kWh
|
- | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,713 | $9,000 |
$448
8,792
kWh
|
$3,432
-
kW-mo/yr
|
$(-167.0)
-
MMBtu
|
|
| 05 | 2.7224: Reduce space conditioning during non-working hours | $2,589 | $2,000 |
$1,141
26,964
kWh
|
- |
$1,448
-
MMBtu
|
|
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,347 | $315 |
$2,347
46,014
kWh
|
- | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $1,195 | $3,000 | - | - |
$1,195
-
MMBtu
|
|
| 08 | 2.2136: Install / repair insulation on steam lines | $1,064 | $3,000 | - | - |
$1,064
-
MMBtu
|
|
| TOTAL RECOMMENDED | $33,465 | $29,315 |
$23,347
521,982
kWh
|
$6,578
-
kW-mo/yr
|
$3,540
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $29,752 | $20,315 |
$22,899
513,190
kWh
|
$3,146
-
kW-mo/yr
|
$3,707
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs