ITAC Assessment: MA0472
ITAC logo
ITAC Assessment: MA0472
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Rubber belting
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 172
Plant Area 200,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 6,420
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $318,052 8,160,024
kWh
Electricity Demand $255,923 23,038
kW-mo/yr
Electricity Fees $21,927 -
Natural Gas $426,474 92,552
MMBtu
Fuel Oil #4 $33,716 6,153
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,465 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,752

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7314: Reduce ventilation air $9,400 - $9,400
239,156
kWh
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,991 $10,000 $5,845
114,596
kWh
$3,146
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $4,166 $2,000 $4,166
86,460
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,713 $9,000 $448
8,792
kWh
$3,432
-
kW-mo/yr
$(-167.0)
-
MMBtu
05 2.7224: Reduce space conditioning during non-working hours $2,589 $2,000 $1,141
26,964
kWh
- $1,448
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,347 $315 $2,347
46,014
kWh
- -
07 2.2136: Install / repair insulation on steam lines $1,195 $3,000 - - $1,195
-
MMBtu
08 2.2136: Install / repair insulation on steam lines $1,064 $3,000 - - $1,064
-
MMBtu
TOTAL RECOMMENDED $33,465 $29,315 $23,347
521,982
kWh
$6,578
-
kW-mo/yr
$3,540
-
MMBtu
TOTAL IMPLEMENTED $29,752 $20,315 $22,899
513,190
kWh
$3,146
-
kW-mo/yr
$3,707
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs