Assessment Year | 2000 |
---|---|
Principal Product | Technical and Specialty Papers |
NAICS |
n/a
|
SIC | 2621: Paper Mills |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
250,000
ft2
|
Annual Production | 36,000
ton
|
Production Hrs. Annual | 8,328
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,005,967 | 16,949,590 |
kWh
|
$0.059 |
Electricity Demand | $161,714 | 39,902 |
kW-mo/yr
|
$4.05 |
Electricity Fees | $807 | - |
|
- |
Fuel Oil #6 | $898,876 | 297,561 |
MMBtu
|
$3.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,322,714 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,489 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.114: Add/modify equipment to improve drying process | $961,067 | $880,000 |
$(-12,310.0)
(-217,468)
kWh
|
$(-1,728.0)
-
kW-mo/yr
|
- |
$(-14,895.0)
-
Tgal
|
- | - | $990,000 | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $194,677 | $430,350 |
$(-58,596.0)
(-1,035,170)
kWh
|
$(-7,413.0)
-
kW-mo/yr
|
$260,686
-
MMBtu
|
- | - | - | - | - | |
03 | 3.4111: Use closed cycle process to minimize waste water production | $113,014 | $750,000 | - | - | - |
$541,651
-
Tgal
|
$(-90,220.0)
-
lb
|
$(-300,917.0) | - | $(-37,500.0) | |
04 | 2.4131: Size electric motors for peak operating efficiency | $14,632 | $31,000 |
$14,632
258,499
kWh
|
- | - | - | - | - | - | - | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $13,500 | $6,000 | - | - | - |
$13,500
-
Tgal
|
- | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,580 | $17,000 |
$11,580
204,572
kWh
|
- | - | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,757 | $1,200 |
$5,923
104,631
kWh
|
$834
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,467 | $14,000 |
$3,467
61,254
kWh
|
- | - | - | - | - | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,406 | $1,200 |
$2,986
52,755
kWh
|
$420
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $614 | $3,575 |
$614
10,844
kWh
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $1,322,714 | $2,134,325 |
$(-31,704.0)
(-560,083)
kWh
|
$(-7,887.0)
-
kW-mo/yr
|
$260,686
-
MMBtu
|
$540,256
-
Tgal
|
$(-90,220.0)
-
lb
|
$(-300,917.0) | $990,000 | $(-37,500.0) | ||
TOTAL IMPLEMENTED | $50,489 | $59,975 |
$35,735
631,301
kWh
|
$1,254
-
kW-mo/yr
|
- |
$13,500
-
Tgal
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs