| Assessment Year | 2000 |
|---|---|
| Principal Product | Yogurt and Cultured Milk Products |
| NAICS |
n/a
|
| SIC | 2026: Fluid Milk |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
77,000
ft2
|
| Annual Production | 88,400,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New Hampshire |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $394,858 | 4,432,884 |
kWh
|
$0.089 |
| Electricity Demand | $82,209 | 10,672 |
kW-mo/yr
|
$7.70 |
| Electricity Fees | $8,137 | - |
|
- |
| LPG | $76,112 | 15,735 |
MMBtu
|
$4.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,766 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,269 | $64,000 |
$7,269
84,408
kWh
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,885 | $6,215 |
$3,029
35,170
kWh
|
$582
-
kW-mo/yr
|
$(-726.0)
-
MMBtu
|
|
| 03 | 2.7135: Install occupancy sensors | $1,161 | $600 |
$1,161
13,482
kWh
|
- | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $963 | $400 | - | - |
$963
-
MMBtu
|
|
| 05 | 2.2628: Utilize a less expensive cooling method | $757 | $1,000 |
$757
8,792
kWh
|
- | - | |
| TOTAL RECOMMENDED | $13,035 | $72,215 |
$12,216
141,852
kWh
|
$582
-
kW-mo/yr
|
$237
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,766 | $8,215 |
$4,947
57,444
kWh
|
$582
-
kW-mo/yr
|
$237
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs