| Assessment Year | 1999 |
|---|---|
| Principal Product | Brake disc pads |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 249 |
| Plant Area |
98,130
ft2
|
| Annual Production | 14,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $404,337 | 6,774,912 |
kWh
|
$0.060 |
| Electricity Demand | $210,473 | 15,370 |
kW-mo/yr
|
$13.69 |
| Electricity Fees | $4,495 | - |
|
- |
| Natural Gas | $170,633 | 40,035 |
MMBtu
|
$4.26 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $143,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $60,085 | $139,425 |
$49,497
770,809
kWh
|
$10,588
-
kW-mo/yr
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $38,897 | $96,900 |
$31,580
491,794
kWh
|
$13,278
-
kW-mo/yr
|
$(-5,961.0)
-
MMBtu
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $19,476 | $45,000 | - | - |
$19,476
-
MMBtu
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,766 | $19,425 |
$7,421
111,372
kWh
|
$3,345
-
kW-mo/yr
|
- | - | |
| 05 | 3.1162: Use less wasteful packaging | $8,714 | $15,000 | - | - | - | $8,714 | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,433 | $10,115 |
$3,750
56,272
kWh
|
$1,683
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $143,371 | $325,865 |
$92,248
1,430,247
kWh
|
$28,894
-
kW-mo/yr
|
$13,515
-
MMBtu
|
$8,714 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs