ITAC Assessment: MA0443
ITAC logo
ITAC Assessment: MA0443
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Medical Needles
NAICS
n/a
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 40,500
ft2
Annual Production 0
units
Production Hrs. Annual 2,860
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,597 509,672
kWh
Electricity Demand $26,517 2,433
kW-mo/yr
Electricity Fees $952 -
Natural Gas $4,608 1,283
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,063 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,662

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,232 $3,510 $1,247
21,688
kWh
$251
-
kW-mo/yr
$(-266.0)
-
MMBtu
02 2.7221: Lower temperature during the winter season and vice-versa $656 $150 $573
9,965
kWh
- $83
-
MMBtu
03 2.7135: Install occupancy sensors $927 $325 $927
16,120
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $287 $1,975 $287
4,982
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $792 $60 $792
13,775
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $169 $160 $169
2,931
kWh
- -
TOTAL RECOMMENDED $4,063 $6,180 $3,995
69,461
kWh
$251
-
kW-mo/yr
$(-183.0)
-
MMBtu
TOTAL IMPLEMENTED $2,662 $2,510 $2,579
44,842
kWh
- $83
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs