| Assessment Year | 1999 |
|---|---|
| Principal Product | High speed spin testing |
| NAICS |
n/a
|
| SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 30 |
| Plant Area |
9,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,310
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,191 | 1,261,137 |
kWh
|
$0.072 |
| Electricity Demand | $64,841 | 6,721 |
kW-mo/yr
|
$9.65 |
| Fuel Oil #2 | $2,491 | 399 |
MMBtu
|
$6.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $301 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $3,090 | $8,125 | - |
$3,090
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $652 | $2,185 |
$456
7,034
kWh
|
$196
-
kW-mo/yr
|
|
| 03 | 2.7135: Install occupancy sensors | $230 | $130 |
$230
4,689
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $71 | $50 |
$71
1,465
kWh
|
- | |
| TOTAL RECOMMENDED | $4,043 | $10,490 |
$757
13,188
kWh
|
$3,286
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $301 | $180 |
$301
6,154
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs