ITAC Assessment: MA0428
ITAC logo
ITAC Assessment: MA0428
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Custom glass to metal sealing, soldering and brazing
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 14,280
ft2
Annual Production 3,000,000
pieces
Production Hrs. Annual 2,375
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,079 520,223
kWh
Electricity Demand $12,254 1,648
kW-mo/yr
LPG $8,329 930
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,338 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,784

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Gaseous Waste Savings By-product Production Savings
01 2.4222: Install adequate dryers on air lines to eliminate blowdown $1,280 $2,110 $(-81.0)
(-879)
kWh
$(-34.0)
-
kW-mo/yr
- $1,395
-
lb
-
02 2.7111: Reduce illumination to minimum necessary levels $642 $30 $437
4,689
kWh
$205
-
kW-mo/yr
- - -
03 2.2437: Recover waste heat from equipment $3,142 $980 $(-54.0)
(-586)
kWh
$(-17.0)
-
kW-mo/yr
$3,213
-
MMBtu
- -
04 4.424: Improve space comfort conditioning $5,656 $11,874 $(-189.0)
(-2,052)
kWh
$(-316.0)
-
kW-mo/yr
- - $6,161
05 4.212: Adopt in-house material generation $5,618 $29,750 $(-3,438.0)
(-37,222)
kWh
$(-1,527.0)
-
kW-mo/yr
- $10,583
-
lb
-
TOTAL RECOMMENDED $16,338 $44,744 $(-3,325.0)
(-36,050)
kWh
$(-1,689.0)
-
kW-mo/yr
$3,213
-
MMBtu
$11,978
-
lb
$6,161
TOTAL IMPLEMENTED $3,784 $1,010 $383
4,103
kWh
$188
-
kW-mo/yr
$3,213
-
MMBtu
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs