Assessment Year | 1998 |
---|---|
Principal Product | Portland cement |
NAICS |
n/a
|
SIC | 3241: Cement, Hydraulic |
Sales Range | $10 M to 50M |
# of Employees | 114 |
Plant Area |
100,000,000
ft2
|
Annual Production | 618,000
ton
|
Production Hrs. Annual | 7,680
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,191,997 | 74,305,394 |
kWh
|
$0.043 |
Electricity Demand | $606,788 | 152,680 |
kW-mo/yr
|
$3.97 |
Coal | $4,840,000 | 3,058,000 |
MMBtu
|
$1.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $519,912 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Coal Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $71,172 | $146,000 |
$71,172
1,582,649
kWh
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $82,915 | $160,000 |
$82,915
1,843,787
kWh
|
- | - | |
03 | 3.5218: Reuse / recycle/ sell rubber products | $264,206 | $700,000 | - |
$386,531
-
MMBtu
|
$(-122,325.0)
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $91,206 | $104,150 |
$91,206
2,028,136
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,320 | $1,650 |
$2,320
51,583
kWh
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,093 | $14,700 |
$8,093
179,953
kWh
|
- | - | |
TOTAL RECOMMENDED | $519,912 | $1,126,500 |
$255,706
5,686,108
kWh
|
$386,531
-
MMBtu
|
$(-122,325.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Coal Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs