Assessment Year | 1999 |
---|---|
Principal Product | Airport Lighting |
NAICS |
n/a
|
SIC | 3648: Lighting Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
66,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,197 | 1,013,482 |
kWh
|
$0.065 |
Electricity Demand | $32,858 | 3,650 |
kW-mo/yr
|
$9.00 |
Natural Gas | $17,748 | 2,442 |
MMBtu
|
$7.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,575 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $3,806 | $300 | - | - |
$3,806
-
MMBtu
|
|
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,841 | $2,700 |
$2,387
37,515
kWh
|
$3,702
-
kW-mo/yr
|
$(-1,248.0)
-
MMBtu
|
|
03 | 2.7224: Reduce space conditioning during non-working hours | $1,343 | $234 |
$1,343
21,102
kWh
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,279 | $80,000 |
$951
14,947
kWh
|
$827
-
kW-mo/yr
|
$(-499.0)
-
MMBtu
|
|
05 | 2.2437: Recover waste heat from equipment | $585 | $2,627 | - | - |
$585
-
MMBtu
|
|
06 | 2.7124: Make a practice of turning off lights when not needed | $187 | $294 |
$187
2,931
kWh
|
- | - | |
07 | 2.7135: Install occupancy sensors | $149 | $257 |
$149
2,345
kWh
|
- | - | |
TOTAL RECOMMENDED | $12,190 | $86,412 |
$5,017
78,840
kWh
|
$4,529
-
kW-mo/yr
|
$2,644
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,575 | $5,861 |
$3,730
58,617
kWh
|
$3,702
-
kW-mo/yr
|
$3,143
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs