ITAC Assessment: MA0423
ITAC logo
ITAC Assessment: MA0423
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Airport Lighting
NAICS
n/a
SIC 3648: Lighting Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 66,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,197 1,013,482
kWh
Electricity Demand $32,858 3,650
kW-mo/yr
Natural Gas $17,748 2,442
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,190 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,575

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $3,806 $300 - - $3,806
-
MMBtu
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $4,841 $2,700 $2,387
37,515
kWh
$3,702
-
kW-mo/yr
$(-1,248.0)
-
MMBtu
03 2.7224: Reduce space conditioning during non-working hours $1,343 $234 $1,343
21,102
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,279 $80,000 $951
14,947
kWh
$827
-
kW-mo/yr
$(-499.0)
-
MMBtu
05 2.2437: Recover waste heat from equipment $585 $2,627 - - $585
-
MMBtu
06 2.7124: Make a practice of turning off lights when not needed $187 $294 $187
2,931
kWh
- -
07 2.7135: Install occupancy sensors $149 $257 $149
2,345
kWh
- -
TOTAL RECOMMENDED $12,190 $86,412 $5,017
78,840
kWh
$4,529
-
kW-mo/yr
$2,644
-
MMBtu
TOTAL IMPLEMENTED $10,575 $5,861 $3,730
58,617
kWh
$3,702
-
kW-mo/yr
$3,143
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs