Assessment Year | 2004 |
---|---|
Principal Product | Plastic thin wall containers |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
175,000
ft2
|
Annual Production | 17,283,861
lb
|
Production Hrs. Annual | 8,592
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,294,615 | 29,426,407 |
kWh
|
$0.044 |
Electricity Demand | $79,366 | 45,791 |
kW-mo/yr
|
$1.73 |
Electricity Fees | $118,195 | - |
|
- |
Natural Gas | $15,569 | 2,323 |
MMBtu
|
$6.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $228,812 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $228,812 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $44,391 | $50 |
$42,289
961,115
kWh
|
$2,102
-
kW-mo/yr
|
- | - | - | |
02 | 2.7232: Replace existing hvac unit with high efficiency model | $2,403 | $240 |
$2,285
52,047
kWh
|
$118
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $743 | $6,446 |
$647
14,744
kWh
|
$96
-
kW-mo/yr
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $736 | $128,880 |
$736
17,389
kWh
|
- | - | - | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $11,254 | $4,200 |
$10,662
242,876
kWh
|
$592
-
kW-mo/yr
|
- | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $516 | $1,697 |
$478
10,884
kWh
|
$38
-
kW-mo/yr
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $17,174 | $840 |
$16,274
370,699
kWh
|
$900
-
kW-mo/yr
|
- | - | - | |
08 | 4.514: Re-arrange equipment layout to reduce handling costs | $6,306 | $300 | - | - |
$936
-
MMBtu
|
$5,370 | - | |
09 | 4.441: Install automatic packing equipment | $128,880 | $850 | - | - | - | $128,880 | - | |
10 | 2.6218: Turn off equipment when not in use | $1,540 | $3,735 |
$1,357
29,283
kWh
|
$183
-
kW-mo/yr
|
- | - | - | |
11 | 4.322: Eliminate old stock and modify inventory control | $4,650 | $36,448 | - | - | - | - | $4,650 | |
12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,219 | $1,125 |
$9,683
220,562
kWh
|
$536
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $228,812 | $184,811 |
$84,411
1,919,599
kWh
|
$4,565
-
kW-mo/yr
|
$936
-
MMBtu
|
$134,250 | $4,650 | ||
TOTAL IMPLEMENTED | $228,812 | $184,811 |
$84,411
1,919,599
kWh
|
$4,565
-
kW-mo/yr
|
$936
-
MMBtu
|
$134,250 | $4,650 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs