| Assessment Year | 1997 |
|---|---|
| Principal Product | Electro-Magnetic Coil Windings |
| NAICS |
n/a
|
| SIC | 3677: Electronic Coils, Transformers, and Other Inductors |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
29,000
ft2
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $123,215 | 1,302,462 |
kWh
|
$0.095 |
| Electricity Demand | $40,052 | 4,198 |
kW-mo/yr
|
$9.54 |
| Natural Gas | $9,762 | 1,111 |
MMBtu
|
$8.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $106,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $106,252 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1191: Change procedures / equipment / operating conditions | $92,750 | $68,000 | - | - | - | $92,750 | |
| 02 | 3.1192: Reduce scrap production | $8,750 | $1,000 | - | - | - | $8,750 | |
| 03 | 2.7135: Install occupancy sensors | $2,550 | $356 |
$2,550
43,669
kWh
|
- | - | - | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $1,895 | $10 |
$1,654
28,429
kWh
|
$241
-
kW-mo/yr
|
- | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $160 | - | - | - |
$160
-
lb
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $147 | - |
$147
2,345
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $106,252 | $69,366 |
$4,351
74,443
kWh
|
$241
-
kW-mo/yr
|
$160
-
lb
|
$101,500 | ||
| TOTAL IMPLEMENTED | $106,252 | $69,366 |
$4,351
74,443
kWh
|
$241
-
kW-mo/yr
|
$160
-
lb
|
$101,500 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs