ITAC Assessment: MA0393
ITAC logo
ITAC Assessment: MA0393
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Electro-Magnetic Coil Windings
NAICS
n/a
SIC 3677: Electronic Coils, Transformers, and Other Inductors
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 29,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 6,500
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $123,215 1,302,462
kWh
Electricity Demand $40,052 4,198
kW-mo/yr
Natural Gas $9,762 1,111
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $106,252 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $106,252

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
01 3.1191: Change procedures / equipment / operating conditions $92,750 $68,000 - - - $92,750
02 3.1192: Reduce scrap production $8,750 $1,000 - - - $8,750
03 2.7135: Install occupancy sensors $2,550 $356 $2,550
43,669
kWh
- - -
04 2.4226: Use / purchase optimum sized compressor $1,895 $10 $1,654
28,429
kWh
$241
-
kW-mo/yr
- -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $160 - - - $160
-
lb
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $147 - $147
2,345
kWh
- - -
TOTAL RECOMMENDED $106,252 $69,366 $4,351
74,443
kWh
$241
-
kW-mo/yr
$160
-
lb
$101,500
TOTAL IMPLEMENTED $106,252 $69,366 $4,351
74,443
kWh
$241
-
kW-mo/yr
$160
-
lb
$101,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs