| Assessment Year | 1997 |
|---|---|
| Principal Product | metal castings |
| NAICS |
n/a
|
| SIC | 3369: Nonferrous Foundries, Except Aluminum and Copper |
| Sales Range | $5 M to 10M |
| # of Employees | 30 |
| Plant Area |
110,000
ft2
|
| Annual Production | 500
ton
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,514 | 1,839,097 |
kWh
|
$0.038 |
| Electricity Demand | $95,161 | 15,972 |
kW-mo/yr
|
$5.96 |
| Natural Gas | $67,663 | 10,010 |
MMBtu
|
$6.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,984 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $35,096 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.522: Modify storage space to avoid rental of a warehouse | $34,500 | $21,950 | - | - | - | - | $34,500 | |
| 02 | 4.652: Replace existing equipment with more suitable substitutes | $8,500 | $3,000 | - | - |
$5,500
-
MMBtu
|
- | $3,000 | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,388 | $6,000 |
$1,049
16,413
kWh
|
$1,845
-
kW-mo/yr
|
$(-506.0)
-
MMBtu
|
- | - | |
| 04 | 2.7132: Install timers on light switches in little used areas | $320 | $268 |
$320
4,982
kWh
|
- | - | - | - | |
| 05 | 3.8133: Convert to aqueous cleaning | $276 | $759 | - | - | - |
$276
-
gal
|
- | |
| TOTAL RECOMMENDED | $45,984 | $31,977 |
$1,369
21,395
kWh
|
$1,845
-
kW-mo/yr
|
$4,994
-
MMBtu
|
$276
-
gal
|
$37,500 | ||
| TOTAL IMPLEMENTED | $35,096 | $22,977 |
$320
4,982
kWh
|
- | - |
$276
-
gal
|
$34,500 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs