| Assessment Year | 1997 |
|---|---|
| Principal Product | Plastic Christmas Tree Stands |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 155 |
| Plant Area |
253,000
ft2
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 6,656
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $168,804 | 2,783,998 |
kWh
|
$0.061 |
| Electricity Demand | $93,059 | 9,540 |
kW-mo/yr
|
$9.75 |
| Electricity Fees | $(-6,448.0) | - |
|
- |
| Natural Gas | $100,135 | 17,901 |
MMBtu
|
$5.59 |
| LPG | $4,544 | 391 |
MMBtu
|
$11.62 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,966 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,681 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,170 | $8,401 |
$7,170
116,354
kWh
|
- | - | - | |
| 02 | 2.2136: Install / repair insulation on steam lines | $1,430 | $1,230 | - |
$1,430
-
MMBtu
|
- | - | |
| 03 | 3.4145: Use magnetic technology to treat water | $2,453 | $5,640 | - | - |
$2,453
-
gal
|
- | |
| 04 | 4.821: Pay bills on time to avoid late fees | $3,251 | - | - | - | - | $3,251 | |
| 05 | 2.2612: Use cooling tower water instead of refrigeration | $5,662 | $21,410 |
$5,662
95,252
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $19,966 | $36,681 |
$12,832
211,606
kWh
|
$1,430
-
MMBtu
|
$2,453
-
gal
|
$3,251 | ||
| TOTAL IMPLEMENTED | $4,681 | $1,230 | - |
$1,430
-
MMBtu
|
- | $3,251 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs