| Assessment Year | 1996 |
|---|---|
| Principal Product | Acoustical Insulation |
| NAICS |
n/a
|
| SIC | 3401: |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
82,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $18,796 | 268,464 |
kWh
|
$0.070 |
| Electricity Demand | $25,793 | 1,734 |
kW-mo/yr
|
$14.87 |
| Natural Gas | $21,159 | 2,409 |
MMBtu
|
$8.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,645 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $843 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $12,250 | $3,800 | - | - | - |
$12,250
-
lb
|
|
| 02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $4,884 | $705 |
$4,884
70,340
kWh
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,081 | $9,888 |
$1,169
16,706
kWh
|
$912
-
kW-mo/yr
|
- | - | |
| 04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $843 | $448 | - | - |
$843
-
MMBtu
|
- | |
| 05 | 2.2443: Re-use or recycle hot or cold process exhaust air | $587 | $2,000 | - | - |
$587
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $20,645 | $16,841 |
$6,053
87,046
kWh
|
$912
-
kW-mo/yr
|
$1,430
-
MMBtu
|
$12,250
-
lb
|
||
| TOTAL IMPLEMENTED | $843 | $448 | - | - |
$843
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs