Assessment Year | 1996 |
---|---|
Principal Product | solid state electronic packages |
NAICS |
n/a
|
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $10 M to 50M |
# of Employees | 349 |
Plant Area |
178,000
ft2
|
Annual Production | 415,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $401,848 | 5,160,317 |
kWh
|
$0.078 |
Electricity Demand | $54,162 | 11,657 |
kW-mo/yr
|
$4.65 |
Natural Gas | $25,105 | 4,212 |
MMBtu
|
$5.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,805 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Gaseous Waste Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.212: Adopt in-house material generation | $21,886 | $11,000 |
$(-2,100.0)
(-22,274)
kWh
|
- | - | - |
$23,986
-
lb
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,735 | $49,531 |
$11,735
170,574
kWh
|
- | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,903 | $8,750 |
$12,892
322,392
kWh
|
- |
$(-7,989.0)
-
MMBtu
|
- | - | |
04 | 3.4145: Use magnetic technology to treat water | $2,500 | $850 | - | - | - |
$2,500
-
lb
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,541 | $3,401 |
$1,541
38,687
kWh
|
- | - | - | - | |
06 | 2.3191: Use demand controller or load shedder | $919 | - | - |
$919
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $43,484 | $73,532 |
$24,068
509,379
kWh
|
$919
-
kW-mo/yr
|
$(-7,989.0)
-
MMBtu
|
$2,500
-
lb
|
$23,986
-
lb
|
||
TOTAL IMPLEMENTED | $22,805 | $11,000 |
$(-2,100.0)
(-22,274)
kWh
|
$919
-
kW-mo/yr
|
- | - |
$23,986
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Gaseous Waste Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs