Assessment Year | 1996 |
---|---|
Principal Product | Printed circuit boards |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
55,000
ft2
|
Annual Production | 140,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,625 | 1,019,930 |
kWh
|
$0.047 |
Electricity Demand | $23,270 | 2,242 |
kW-mo/yr
|
$10.38 |
Electricity Fees | $7,646 | - |
|
- |
Natural Gas | $82,286 | 14,682 |
MMBtu
|
$5.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,726 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,784 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 3.4113: Treat and reuse rinse waters | $17,190 | $12,000 | - | - |
$17,190
-
Tgal
|
|
02 | 2.2612: Use cooling tower water instead of refrigeration | $8,710 | $25,500 |
$1,030
60,375
kWh
|
- |
$7,680
-
Tgal
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,509 | $11,189 |
$2,509
57,737
kWh
|
- | - | |
04 | 2.2113: Repair or replace steam traps | $1,990 | $868 | - |
$1,990
-
MMBtu
|
- | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,042 | $2,804 |
$3,562
80,305
kWh
|
$(-1,520.0)
-
MMBtu
|
- | |
06 | 2.2122: Install / repair insulation on condensate lines | $285 | $460 |
$285
14,947
kWh
|
- | - | |
TOTAL RECOMMENDED | $32,726 | $52,821 |
$7,386
213,364
kWh
|
$470
-
MMBtu
|
$24,870
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,784 | $12,517 |
$2,794
72,684
kWh
|
$1,990
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs