Assessment Year | 1996 |
---|---|
Principal Product | Commercial steel treating |
NAICS |
n/a
|
SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 41 |
Plant Area |
38,400
ft2
|
Annual Production | 365,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $296,805 | 5,545,721 |
kWh
|
$0.054 |
Electricity Demand | $127,880 | 13,488 |
kW-mo/yr
|
$9.48 |
Natural Gas | $79,999 | 16,327 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,314 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $774 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.212: Adopt in-house material generation | $20,546 | $119,500 |
$(-5,530.0)
(-216,882)
kWh
|
$(-274.0)
-
kW-mo/yr
|
- | - | - | $26,350 | |
02 | 3.4114: Replace city water with recycled water via cooling tower | $5,996 | $2,009 | - | - | - |
$5,996
-
Tgal
|
- | - | |
03 | 2.2442: Preheat combustion air with waste heat | $652 | $12,000 | - | - |
$652
-
MMBtu
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,606 | - |
$1,931
61,254
kWh
|
- | - | - | $(-325.0) | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,454 | $900 |
$1,454
24,619
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $755 | $4,800 |
$755
23,740
kWh
|
- | - | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $477 | $1,100 |
$477
15,533
kWh
|
- | - | - | - | - | |
08 | 2.7314: Reduce ventilation air | $360 | - |
$360
14,068
kWh
|
- | - | - | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $297 | - |
$297
9,672
kWh
|
- | - | - | - | - | |
10 | 2.7135: Install occupancy sensors | $171 | $237 |
$171
5,569
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $32,314 | $140,546 |
$(-85.0)
(-62,427)
kWh
|
$(-274.0)
-
kW-mo/yr
|
$652
-
MMBtu
|
$5,996
-
Tgal
|
$(-325.0) | $26,350 | ||
TOTAL IMPLEMENTED | $774 | $1,100 |
$774
25,205
kWh
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs