Assessment Year | 1996 |
---|---|
Principal Product | paper |
NAICS |
n/a
|
SIC | 2621: Paper Mills |
Sales Range | $5 M to 10M |
# of Employees | 89 |
Plant Area |
333,000
ft2
|
Annual Production | 7,500,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $334,482 | 5,470,692 |
kWh
|
$0.061 |
Electricity Demand | $54,792 | 26,547 |
kW-mo/yr
|
$2.06 |
Electricity Fees | $6,996 | - |
|
- |
Other Energy | $411,341 | 80,400 |
MMBtu
|
$5.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $207,320 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $164,672 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Energy Savings | Water Disposal Savings | Primary Raw Material Savings | Water Consumption Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3322: Use existing dam to generate electricity | $109,702 | $40,000 |
$102,709
1,974,209
kWh
|
- | - | - | - | - | - | $6,993 | |
02 | 3.4111: Use closed cycle process to minimize waste water production | $30,286 | $11,000 | - | - | - | - |
$3,301
-
Tgal
|
$26,985 | - | - | |
03 | 2.2113: Repair or replace steam traps | $29,467 | $6,350 | - | - | - |
$29,467
-
MMBtu
|
- | - | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $18,658 | $18,595 | - | - | - |
$18,658
-
MMBtu
|
- | - | - | - | |
05 | 2.8123: Pay utility bills on time | $10,690 | - | - | - | $3,512 | - | - | - |
$7,178
-
Tgal
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,026 | $14,436 |
$5,645
92,321
kWh
|
$381
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.7135: Install occupancy sensors | $1,613 | $280 |
$1,613
26,377
kWh
|
- | - | - | - | - | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $878 | $902 |
$878
14,361
kWh
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $207,320 | $91,563 |
$110,845
2,107,268
kWh
|
$381
-
kW-mo/yr
|
$3,512 |
$48,125
-
MMBtu
|
$3,301
-
Tgal
|
$26,985 |
$7,178
-
Tgal
|
$6,993 | ||
TOTAL IMPLEMENTED | $164,672 | $84,031 |
$108,354
2,066,530
kWh
|
$381
-
kW-mo/yr
|
- |
$18,658
-
MMBtu
|
$3,301
-
Tgal
|
$26,985 | - | $6,993 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Energy Savings | Water Disposal Savings | Primary Raw Material Savings | Water Consumption Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs