ITAC Assessment: MA0353
ITAC logo
ITAC Assessment: MA0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product aerospace metal stampings
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 100,000
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $168,766 3,134,232
kWh
Electricity Demand $89,269 10,342
kW-mo/yr
Electricity Fees $4,765 -
LPG $1,921 165
MMBtu
Fuel Oil #4 $73,031 16,777
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,139 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,470

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #4 Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $19,522 $57,000 $14,912
250,586
kWh
$4,610
-
kW-mo/yr
- - -
02 3.8143: Recycle cleaning solvent and reuse $5,470 - - - - $2,500
-
gal
$2,970
03 2.2694: Use highest temperature for chilling or cold storage $2,724 $5,000 $2,724
45,721
kWh
- - - -
04 2.7224: Reduce space conditioning during non-working hours $1,018 $1,720 - - $1,018
-
MMBtu
- -
05 2.4314: Use synthetic lubricant $405 - $405
8,499
kWh
- - - -
TOTAL RECOMMENDED $29,139 $63,720 $18,041
304,806
kWh
$4,610
-
kW-mo/yr
$1,018
-
MMBtu
$2,500
-
gal
$2,970
TOTAL IMPLEMENTED $5,470 - - - - $2,500
-
gal
$2,970
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs