ITAC Assessment: MA0351
ITAC logo
ITAC Assessment: MA0351
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Shoe manufacturing machinery
NAICS
n/a
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 105,000
ft2
Annual Production 900
pieces
Production Hrs. Annual 4,290
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $81,669 922,333
kWh
Electricity Demand $46,450 3,489
kW-mo/yr
Electricity Fees $1,292 -
Natural Gas $12,330 1,849
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,874 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,882

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $20,496 $95,712 $14,698
159,144
kWh
$5,798
-
kW-mo/yr
- - -
02 2.7229: Air condition only space necessary $10,096 $26,690 $4,846
52,462
kWh
- $5,250
-
MMBtu
- -
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,105 $2,750 - - - - $3,105
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,400 $2,200 - - - $2,400
-
lb
-
05 2.7135: Install occupancy sensors $1,777 $770 $1,777
19,343
kWh
- - - -
TOTAL RECOMMENDED $37,874 $128,122 $21,321
230,949
kWh
$5,798
-
kW-mo/yr
$5,250
-
MMBtu
$2,400
-
lb
$3,105
TOTAL IMPLEMENTED $4,882 $3,520 $1,777
19,343
kWh
- - - $3,105
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs