| Assessment Year | 1995 |
|---|---|
| Principal Product | Zinc Die Castings |
| NAICS |
n/a
|
| SIC | 3364: Nonferrous Die-Castings, Except Aluminum |
| Sales Range | $1 M to 5M |
| # of Employees | 37 |
| Plant Area |
11,188
ft2
|
| Annual Production | 1,350,000
lb
|
| Production Hrs. Annual | 3,875
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $52,831 | 400,645 |
kWh
|
$0.13 |
| Natural Gas | $75,174 | 9,984 |
MMBtu
|
$7.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,942 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $26,616 | $37,300 | - | - | - | $26,616 | |
| 02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $8,446 | $9,000 |
$(-661.0)
(-7,034)
kWh
|
- |
$9,107
-
Tgal
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $2,559 | $3,300 |
$2,559
31,360
kWh
|
- | - | - | |
| 04 | 2.1115: Eliminate combustible gas in flue gas | $2,131 | $1,750 | - |
$2,131
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,114 | $6,330 |
$2,114
16,120
kWh
|
- | - | - | |
| 06 | 2.2514: Cover open tanks | $828 | $274 | - |
$828
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $42,694 | $57,954 |
$4,012
40,446
kWh
|
$2,959
-
MMBtu
|
$9,107
-
Tgal
|
$26,616 | ||
| TOTAL IMPLEMENTED | $2,942 | $6,604 |
$2,114
16,120
kWh
|
$828
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs