ITAC Assessment: MA0343
ITAC logo
ITAC Assessment: MA0343
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Zinc Die Castings
NAICS
n/a
SIC 3364: Nonferrous Die-Castings, Except Aluminum
Sales Range $1
M
to 5
M
# of Employees 37
Plant Area 11,188
ft2
Annual Production 1,350,000
lb
Production Hrs. Annual 3,875
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,831 400,645
kWh
Natural Gas $75,174 9,984
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,694 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,942

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $26,616 $37,300 - - - $26,616
02 2.2614: Use cooling tower or economizer to replace chiller cooling $8,446 $9,000 $(-661.0)
(-7,034)
kWh
- $9,107
-
Tgal
-
03 2.4239: Eliminate or reduce compressed air usage $2,559 $3,300 $2,559
31,360
kWh
- - -
04 2.1115: Eliminate combustible gas in flue gas $2,131 $1,750 - $2,131
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,114 $6,330 $2,114
16,120
kWh
- - -
06 2.2514: Cover open tanks $828 $274 - $828
-
MMBtu
- -
TOTAL RECOMMENDED $42,694 $57,954 $4,012
40,446
kWh
$2,959
-
MMBtu
$9,107
-
Tgal
$26,616
TOTAL IMPLEMENTED $2,942 $6,604 $2,114
16,120
kWh
$828
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs