ITAC Assessment: MA0326
ITAC logo
ITAC Assessment: MA0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Heat transfer printings
NAICS
n/a
SIC 2297: Non-woven Fabrics
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 46,500
ft2
Annual Production 120,000,000
pieces
Production Hrs. Annual 5,304
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $272,370 2,786,342
kWh
Natural Gas $19,983 2,103
MMBtu
Fuel Oil #2 $11,545 1,964
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,738 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,993

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
01 2.3134: Shift from daytime to nighttime operation $26,014 $2,700 $1,014
-
kWh
- $25,000
02 2.7111: Reduce illumination to minimum necessary levels $9,865 $288 $9,865
100,821
kWh
- -
03 2.2511: Insulate bare equipment $4,443 $7,770 $4,443
45,428
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $2,604 $4,305 - $2,604
-
MMBtu
-
05 2.2437: Recover waste heat from equipment $2,293 $2,500 $2,293
23,447
kWh
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,920 - $1,920
19,637
kWh
- -
07 2.7135: Install occupancy sensors $946 $986 $946
9,672
kWh
- -
08 2.7224: Reduce space conditioning during non-working hours $653 $836 - $653
-
MMBtu
-
TOTAL RECOMMENDED $48,738 $19,385 $20,481
199,005
kWh
$3,257
-
MMBtu
$25,000
TOTAL IMPLEMENTED $9,993 $15,411 $6,736
68,875
kWh
$3,257
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs