ITAC Assessment: MA0314
ITAC logo
ITAC Assessment: MA0314
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product leather welts
NAICS
n/a
SIC 3131: Boot and Shoe Cut Stock and Findings
Sales Range $5
M
to 10
M
# of Employees 52
Plant Area 158,184
ft2
Annual Production 150,000
pieces
Production Hrs. Annual 2,375
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,713 905,920
kWh
Fuel Oil #4 $56,568 14,374
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,727 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,672

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #4 Savings Water Disposal Savings Other Liquid (haz) Savings
01 2.2113: Repair or replace steam traps $3,446 $2,662 - $3,446
-
MMBtu
- -
02 2.7224: Reduce space conditioning during non-working hours $1,971 $861 $1,971
18,464
kWh
- - -
03 2.1331: Burn a less expensive grade of fuel $2,302 $2,233 $2,703
25,205
kWh
$(-401.0)
-
MMBtu
- -
04 2.7135: Install occupancy sensors $782 $1,284 $782
7,034
kWh
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $469 - $469
4,396
kWh
- - -
06 3.4115: Recover and reuse cooling water $2,833 $3,454 $1,533
14,361
kWh
- $1,300
-
Tgal
-
07 3.8131: Use water-based adhesives $16,924 - - - - $16,924
-
gal
TOTAL RECOMMENDED $28,727 $10,494 $7,458
69,460
kWh
$3,045
-
MMBtu
$1,300
-
Tgal
$16,924
-
gal
TOTAL IMPLEMENTED $23,672 $6,116 $2,002
18,757
kWh
$3,446
-
MMBtu
$1,300
-
Tgal
$16,924
-
gal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #4 Savings Water Disposal Savings Other Liquid (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs