ITAC Assessment: MA0285
ITAC logo
ITAC Assessment: MA0285
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product drafting paper
NAICS
n/a
SIC 3952: Lead Pencils, Crayons, and Artists' Materials
Sales Range $10
M
to 50
M
# of Employees 101
Plant Area 108,000
ft2
Annual Production 37,666
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $344,878 3,803,048
kWh
Natural Gas $340,491 51,231
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $230,611 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,214

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Consumption Savings
01 2.8113: Purchase gas directly from a contract gas supplier $109,286 $73,056 - $109,286
-
MMBtu
-
02 2.2437: Recover waste heat from equipment $55,888 $14,720 - $55,888
-
MMBtu
-
03 2.1224: Replace boiler $26,214 - - $26,214
-
MMBtu
-
04 2.7491: Insulate glazing, walls, ceilings, and roofs $20,398 $47,520 - $20,398
-
MMBtu
-
05 2.2437: Recover waste heat from equipment $9,189 $7,537 - $9,189
-
MMBtu
-
06 3.4115: Recover and reuse cooling water $4,616 $385 $(-266.0)
(-2,931)
kWh
- $4,882
-
Tgal
07 2.7142: Utilize higher efficiency lamps and/or ballasts $4,120 $7,480 $4,120
47,186
kWh
- -
08 2.2136: Install / repair insulation on steam lines $900 $320 - $900
-
MMBtu
-
TOTAL RECOMMENDED $230,611 $151,018 $3,854
44,255
kWh
$221,875
-
MMBtu
$4,882
-
Tgal
TOTAL IMPLEMENTED $26,214 - - $26,214
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs