ITAC Assessment: MA0266
ITAC logo
ITAC Assessment: MA0266
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product External analgetics
NAICS
n/a
SIC 2833: Medicinal Chemicals and Botanical Products
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 65,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,541 372,509
kWh
Natural Gas $13,323 1,926
MMBtu
Fuel Oil #2 $5,326 1,050
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,567 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,373

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,208 $1,950 $1,208
9,672
kWh
-
02 2.7231: Use radiant heater for spot heating $922 - - $922
-
MMBtu
03 2.7135: Install occupancy sensors $695 $419 $695
5,569
kWh
-
04 2.1233: Analyze flue gas for proper air/fuel ratio $470 $400 - $470
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $146 - $146
1,172
kWh
-
06 2.7314: Reduce ventilation air $126 $75 $126
2,052
kWh
-
TOTAL RECOMMENDED $3,567 $2,844 $2,175
18,465
kWh
$1,392
-
MMBtu
TOTAL IMPLEMENTED $2,373 $2,769 $1,903
15,241
kWh
$470
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs