| Assessment Year | 1992 |
|---|---|
| Principal Product | PVC COMPOUND |
| NAICS |
n/a
|
| SIC | 3087: Custom Compounding of Purchased Plastics Resins |
| Sales Range | $10 M to 50M |
| # of Employees | 135 |
| Plant Area |
n/a
|
| Annual Production | 55,000,000
lb
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $596,595 | 7,202,814 |
kWh
|
$0.083 |
| LPG | $31,708 | 359,622 |
MMBtu
|
$0.088 |
| Fuel Oil #4 | $72,279 | 20,182 |
MMBtu
|
$3.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,445 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,143 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #4 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2113: Repair or replace steam traps | $5,378 | $1 | - |
$7,178
-
MMBtu
|
$(-1,800.0) | |
| 02 | 2.2511: Insulate bare equipment | $5,818 | $10,368 | - |
$5,818
-
MMBtu
|
- | |
| 03 | 2.2136: Install / repair insulation on steam lines | $4,995 | $4,022 | - |
$4,995
-
MMBtu
|
- | |
| 04 | 2.1213: Direct warmest air to combustion intake | $840 | $647 | - |
$840
-
MMBtu
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $637 | $1,661 | - |
$637
-
MMBtu
|
- | |
| 06 | 2.2511: Insulate bare equipment | $480 | $530 | - |
$480
-
MMBtu
|
- | |
| 07 | 2.2122: Install / repair insulation on condensate lines | $290 | $90 | - |
$290
-
MMBtu
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,007 | - |
$1,076
12,896
kWh
|
- | $(-69.0) | |
| TOTAL RECOMMENDED | $19,445 | $17,319 |
$1,076
12,896
kWh
|
$20,238
-
MMBtu
|
$(-1,869.0) | ||
| TOTAL IMPLEMENTED | $11,143 | $4,643 | - |
$12,943
-
MMBtu
|
$(-1,800.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #4 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs