ITAC Assessment: MA0245
ITAC logo
ITAC Assessment: MA0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PLASTIC INJECTION MOLDS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 31
Plant Area
n/a
Annual Production 300,000
lb
Production Hrs. Annual 5,928
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,138 703,107
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,798 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,482

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $6,316 - $8,624
100,821
kWh
$(-2,308.0)
-
MMBtu
02 2.5194: Redesign process $4,412 $1,554 $4,412
51,583
kWh
-
03 3.4115: Recover and reuse cooling water $2,833 $5,040 $2,833
33,118
kWh
-
04 2.6212: Turn off equipment during breaks, reduce operating time $4,237 - $4,237
49,531
kWh
-
TOTAL RECOMMENDED $17,798 $6,594 $20,106
235,053
kWh
$(-2,308.0)
-
MMBtu
TOTAL IMPLEMENTED $11,482 $6,594 $11,482
134,232
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs