ITAC Assessment: MA0241
ITAC logo
ITAC Assessment: MA0241
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product SILICONE RUBBER HOSES
NAICS
n/a
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,335
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $109,127 787,808
kWh
Fuel Oil #2 $26,466 5,040
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,178 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,589

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
01 3.4115: Recover and reuse cooling water $15,035 $1 $(-1,380.0)
(-9,965)
kWh
- $16,415
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,491 - $1,850
13,482
kWh
- $(-359.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,299 $3,325 $1,299
9,379
kWh
- -
04 2.2113: Repair or replace steam traps $2,740 $2 - $3,365
-
MMBtu
$(-625.0)
05 2.2122: Install / repair insulation on condensate lines $530 $117 - $530
-
MMBtu
-
06 2.2511: Insulate bare equipment $515 $245 - $515
-
MMBtu
-
07 2.4312: Improve lubrication practices $284 - $284
2,052
kWh
- -
08 2.4221: Install compressor air intakes in coolest locations $284 $241 $284
2,052
kWh
- -
TOTAL RECOMMENDED $22,178 $3,931 $2,337
17,000
kWh
$4,410
-
MMBtu
$15,431
TOTAL IMPLEMENTED $19,589 $3,573 $(-81.0)
(-586)
kWh
$3,880
-
MMBtu
$15,790
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs