Assessment Year | 1992 |
---|---|
Principal Product | COATED COPPER CABLES |
NAICS |
n/a
|
SIC | 3351: Rolling, Drawing, and Extruding Of Copper |
Sales Range | $50 M to 100M |
# of Employees | 283 |
Plant Area |
n/a
|
Annual Production | 350,000
thousand feet
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,252,177 | 13,800,117 |
kWh
|
$0.091 |
Natural Gas | $136,396 | 46,341 |
MMBtu
|
$2.94 |
Fuel Oil #6 | $77,345 | 23,910 |
MMBtu
|
$3.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,943 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $52,287 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #6 Savings |
---|---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $28,770 | $2,000 |
$28,770
317,116
kWh
|
- | - | |
02 | 2.2625: Chill water to the highest temperature possible | $4,263 | - |
$4,263
46,893
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $10,672 | $12,412 | - |
$6,815
-
MMBtu
|
$3,857
-
MMBtu
|
|
04 | 2.2414: Use waste heat from hot flue gases to preheat | $7,341 | $14,210 | - |
$7,341
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,334 | $8,000 |
$4,334
47,773
kWh
|
- | - | |
06 | 2.2191: Substitute hot process fluids for steam | $2,393 | $10,000 | - |
$1,527
-
MMBtu
|
$866
-
MMBtu
|
|
07 | 2.4312: Improve lubrication practices | $1,170 | - |
$1,170
12,896
kWh
|
- | - | |
TOTAL RECOMMENDED | $58,943 | $46,622 |
$38,537
424,678
kWh
|
$15,683
-
MMBtu
|
$4,723
-
MMBtu
|
||
TOTAL IMPLEMENTED | $52,287 | $36,622 |
$34,274
377,785
kWh
|
$14,156
-
MMBtu
|
$3,857
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #6 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs