Assessment Year | 1991 |
---|---|
Principal Product | POWER CORDS |
NAICS |
n/a
|
SIC | 3351: Rolling, Drawing, and Extruding Of Copper |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
n/a
|
Annual Production | 175
thousand feet
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $333,778 | 4,033,118 |
kWh
|
$0.083 |
Natural Gas | $5,843 | 879 |
MMBtu
|
$6.65 |
Fuel Oil #4 | $166,504 | 34,795 |
MMBtu
|
$4.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $111,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #4 Savings |
---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $51,002 | $4,050 | - |
$51,002
-
MMBtu
|
|
02 | 2.2414: Use waste heat from hot flue gases to preheat | $13,862 | $19,305 | - |
$13,862
-
MMBtu
|
|
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $11,453 | $1,500 | - |
$11,453
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,357 | $30,000 |
$9,357
113,423
kWh
|
- | |
05 | 2.5123: Reduce fluid flow rates | $8,252 | $330 |
$8,252
99,941
kWh
|
- | |
06 | 2.7226: Use computer programs to optimize hvac performance | $7,199 | - | - |
$7,199
-
MMBtu
|
|
07 | 2.2136: Install / repair insulation on steam lines | $5,777 | $3,874 | - |
$5,777
-
MMBtu
|
|
08 | 2.6218: Turn off equipment when not in use | $2,370 | - |
$2,370
28,722
kWh
|
- | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $998 | - |
$998
12,016
kWh
|
- | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $920 | $1,839 |
$920
11,137
kWh
|
- | |
TOTAL RECOMMENDED | $111,190 | $60,898 |
$21,897
265,239
kWh
|
$89,293
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #4 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs