ITAC Assessment: MA0185
ITAC logo
ITAC Assessment: MA0185
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product CUSTOM PROFILE EXTRUSION
NAICS
n/a
SIC 3082: Unsupported Plastics Profile Shapes
Sales Range $5
M
to 10
M
# of Employees 71
Plant Area
n/a
Annual Production 3,283,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $118,072 1,626,026
kWh
Fuel Oil #2 $18,689 2,570
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,770 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,412

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.3212: Optimize plant power factor $9,738 $10,200 $9,738
-
kWh
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,358 - $3,358
-
kWh
-
03 2.6121: Reduce hot water temperature to the minimum required $334 $180 - $334
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $340 $471 $340
4,689
kWh
-
TOTAL RECOMMENDED $13,770 $10,851 $13,436
4,689
kWh
$334
-
MMBtu
TOTAL IMPLEMENTED $10,412 $10,851 $10,078
4,689
kWh
$334
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs