ITAC Assessment: MA0160
ITAC logo
ITAC Assessment: MA0160
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product CHAFF FOR RADAR SYSTEMS
NAICS
n/a
SIC 3483: Ammunition, Except for Small Arms
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 12,500
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,734 551,876
kWh
Natural Gas $13,572 2,430
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,181 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,142

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $364 $535 $364
3,810
kWh
02 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $434 - $434
4,396
kWh
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,675 $1,000 $1,675
17,585
kWh
04 2.7226: Use computer programs to optimize hvac performance $1,708 $1,000 $1,708
17,878
kWh
TOTAL RECOMMENDED $4,181 $2,535 $4,181
43,669
kWh
TOTAL IMPLEMENTED $2,142 $1,000 $2,142
22,274
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs