ITAC Assessment: MA0153
ITAC logo
ITAC Assessment: MA0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product FLUID MILK PRODUCTS
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 20,000
Tgal
Production Hrs. Annual 7,344
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $331,966 5,096,131
kWh
Natural Gas $54,082 15,516
MMBtu
Fuel Oil #2 $13,604 2,881
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,187 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,703

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $632 $217 $632
9,672
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $878 $163 $878
13,482
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,825 $500 $2,209
33,998
kWh
- - $1,616
04 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust $19,722 $115,000 $36,262
550,703
kWh
$(-7,360.0)
-
MMBtu
- $(-9,180.0)
05 2.3191: Use demand controller or load shedder $3,985 $1,910 $3,985
-
kWh
- - -
06 2.1131: Repair faulty insulation in furnaces, boilers, etc $530 $218 - $423
-
MMBtu
$107
-
MMBtu
-
07 2.7226: Use computer programs to optimize hvac performance $2,615 $3,000 $2,615
40,152
kWh
- - -
TOTAL RECOMMENDED $32,187 $121,008 $46,581
648,007
kWh
$(-6,937.0)
-
MMBtu
$107
-
MMBtu
$(-7,564.0)
TOTAL IMPLEMENTED $4,703 $663 $3,087
47,480
kWh
- - $1,616
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs