Assessment Year | 1989 |
---|---|
Principal Product | TANTALUM CAPACITORS |
NAICS |
n/a
|
SIC | 3675: Electronic Capacitors |
Sales Range | $10 M to 50M |
# of Employees | 148 |
Plant Area |
n/a
|
Annual Production | 20,000,000
pieces
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Vermont |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $212,993 | 2,589,097 |
kWh
|
$0.082 |
LPG | $3,810 | 396 |
MMBtu
|
$9.62 |
Fuel Oil #2 | $12,326 | 2,316 |
MMBtu
|
$5.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,996 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,986 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,378 | $527 |
$1,378
16,706
kWh
|
- | - | |
02 | 2.7492: Use proper thickness of insulation on building envelope | $7,925 | $40,371 |
$4,680
66,530
kWh
|
- |
$3,245
-
MMBtu
|
|
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,765 | $2,300 |
$2,210
19,637
kWh
|
- |
$(-445.0)
-
MMBtu
|
|
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,320 | $18,000 |
$8,130
98,769
kWh
|
$(-3,810.0)
-
MMBtu
|
- | |
05 | 2.7224: Reduce space conditioning during non-working hours | $208 | - | - | - |
$208
-
MMBtu
|
|
06 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $400 | - |
$400
4,982
kWh
|
- | - | |
TOTAL RECOMMENDED | $15,996 | $61,198 |
$16,798
206,624
kWh
|
$(-3,810.0)
-
MMBtu
|
$3,008
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,986 | $527 |
$1,778
21,688
kWh
|
- |
$208
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs