ITAC Assessment: MA0141
ITAC logo
ITAC Assessment: MA0141
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product MECH. TIMING DEVICES
NAICS
n/a
SIC 3625: Relays and Industrial Controls
Sales Range $5
M
to 10
M
# of Employees 130
Plant Area
n/a
Annual Production 1,500,000
pieces
Production Hrs. Annual 2,082
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,627 1,383,939
kWh
Natural Gas $15,195 2,267
MMBtu
Fuel Oil #2 $20,735 4,879
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,425 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,514

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7492: Use proper thickness of insulation on building envelope $13,473 $65,600 - $13,473
-
MMBtu
02 2.7226: Use computer programs to optimize hvac performance $6,357 $9,450 $6,357
87,925
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $2,062 $700 $2,062
26,964
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $716 $200 $716
9,379
kWh
-
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $950 $2,200 $1,520
19,930
kWh
$(-570.0)
-
MMBtu
06 2.2443: Re-use or recycle hot or cold process exhaust air $961 $3,000 $961
12,603
kWh
-
07 2.6242: Minimize operation of equipment maintained in standby condition $1,906 - $1,906
24,912
kWh
-
TOTAL RECOMMENDED $26,425 $81,150 $13,522
181,713
kWh
$12,903
-
MMBtu
TOTAL IMPLEMENTED $24,514 $75,950 $11,041
149,180
kWh
$13,473
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs