| Assessment Year | 1988 |
|---|---|
| Principal Product | MECH. TIMING DEVICES |
| NAICS |
n/a
|
| SIC | 3625: Relays and Industrial Controls |
| Sales Range | $5 M to 10M |
| # of Employees | 130 |
| Plant Area |
n/a
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 2,082
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,627 | 1,383,939 |
kWh
|
$0.076 |
| Natural Gas | $15,195 | 2,267 |
MMBtu
|
$6.70 |
| Fuel Oil #2 | $20,735 | 4,879 |
MMBtu
|
$4.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,425 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,514 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $13,473 | $65,600 | - |
$13,473
-
MMBtu
|
|
| 02 | 2.7226: Use computer programs to optimize hvac performance | $6,357 | $9,450 |
$6,357
87,925
kWh
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $2,062 | $700 |
$2,062
26,964
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $716 | $200 |
$716
9,379
kWh
|
- | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $950 | $2,200 |
$1,520
19,930
kWh
|
$(-570.0)
-
MMBtu
|
|
| 06 | 2.2443: Re-use or recycle hot or cold process exhaust air | $961 | $3,000 |
$961
12,603
kWh
|
- | |
| 07 | 2.6242: Minimize operation of equipment maintained in standby condition | $1,906 | - |
$1,906
24,912
kWh
|
- | |
| TOTAL RECOMMENDED | $26,425 | $81,150 |
$13,522
181,713
kWh
|
$12,903
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $24,514 | $75,950 |
$11,041
149,180
kWh
|
$13,473
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs