ITAC Assessment: MA0121
ITAC logo
ITAC Assessment: MA0121
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product MOLDED RUBBER PRODUCTS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 125
Plant Area
n/a
Annual Production 16,315,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $422,998 5,946,659
kWh
Natural Gas $5,918 854
MMBtu
Fuel Oil #6 $80,085 25,735
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,977 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,995

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #6 Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $3,877 - - $4,727
-
MMBtu
$(-850.0)
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,535 $400 $5,535
77,960
kWh
- -
03 2.1213: Direct warmest air to combustion intake $992 $251 - $992
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $2,017 $200 $2,017
28,429
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,134 $187 $1,134
15,826
kWh
- -
06 2.4131: Size electric motors for peak operating efficiency $7,432 $6,690 $7,432
104,338
kWh
- -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $458 - $458
6,448
kWh
- -
08 2.2511: Insulate bare equipment $17,117 $296 $17,117
240,621
kWh
- -
09 2.6241: Reduce temperature of process equipment when on standby $5,108 $4,000 $5,108
71,805
kWh
- -
10 2.4322: Use or replace with energy efficient substitutes $5,646 $3,015 $5,646
79,426
kWh
- -
11 2.2491: Use cooling air which cools hot work pieces for space heating $10,661 $15,422 $(-159.0)
(-2,345)
kWh
$10,820
-
MMBtu
-
TOTAL RECOMMENDED $59,977 $30,461 $44,288
622,508
kWh
$16,539
-
MMBtu
$(-850.0)
TOTAL IMPLEMENTED $19,995 $7,477 $16,118
226,553
kWh
$4,727
-
MMBtu
$(-850.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #6 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs