Assessment Year | 1988 |
---|---|
Principal Product | MOLDED RUBBER PRODUCTS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 125 |
Plant Area |
n/a
|
Annual Production | 16,315,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $422,998 | 5,946,659 |
kWh
|
$0.071 |
Natural Gas | $5,918 | 854 |
MMBtu
|
$6.93 |
Fuel Oil #6 | $80,085 | 25,735 |
MMBtu
|
$3.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,977 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,995 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,877 | - | - |
$4,727
-
MMBtu
|
$(-850.0) | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,535 | $400 |
$5,535
77,960
kWh
|
- | - | |
03 | 2.1213: Direct warmest air to combustion intake | $992 | $251 | - |
$992
-
MMBtu
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,017 | $200 |
$2,017
28,429
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,134 | $187 |
$1,134
15,826
kWh
|
- | - | |
06 | 2.4131: Size electric motors for peak operating efficiency | $7,432 | $6,690 |
$7,432
104,338
kWh
|
- | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $458 | - |
$458
6,448
kWh
|
- | - | |
08 | 2.2511: Insulate bare equipment | $17,117 | $296 |
$17,117
240,621
kWh
|
- | - | |
09 | 2.6241: Reduce temperature of process equipment when on standby | $5,108 | $4,000 |
$5,108
71,805
kWh
|
- | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $5,646 | $3,015 |
$5,646
79,426
kWh
|
- | - | |
11 | 2.2491: Use cooling air which cools hot work pieces for space heating | $10,661 | $15,422 |
$(-159.0)
(-2,345)
kWh
|
$10,820
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $59,977 | $30,461 |
$44,288
622,508
kWh
|
$16,539
-
MMBtu
|
$(-850.0) | ||
TOTAL IMPLEMENTED | $19,995 | $7,477 |
$16,118
226,553
kWh
|
$4,727
-
MMBtu
|
$(-850.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs