Assessment Year | 1987 |
---|---|
Principal Product | MOLDED PLASTIC CMPONENTS |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 2,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $208,599 | 2,737,104 |
kWh
|
$0.076 |
Fuel Oil #2 | $8,061 | 2,090 |
MMBtu
|
$3.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,570 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,468 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,581 | $551 |
$1,743
22,860
kWh
|
$(-162.0)
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $402 | $78 |
$402
5,275
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $1,922 | $746 | - |
$1,922
-
MMBtu
|
|
04 | 2.7261: Install timers and/or thermostats | $715 | $450 |
$715
9,379
kWh
|
- | |
05 | 2.2511: Insulate bare equipment | $1,966 | $1,014 |
$2,167
28,429
kWh
|
$(-201.0)
-
MMBtu
|
|
06 | 2.7243: Improve air circulation with destratification fans / other methods | $2,391 | $893 |
$(-849.0)
(-11,137)
kWh
|
$3,240
-
MMBtu
|
|
07 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $22,563 | $4,750 |
$22,563
296,014
kWh
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $43,030 | $3,900 |
$43,030
566,237
kWh
|
- | |
TOTAL RECOMMENDED | $74,570 | $12,382 |
$69,771
917,057
kWh
|
$4,799
-
MMBtu
|
||
TOTAL IMPLEMENTED | $26,468 | $6,125 |
$24,708
324,149
kWh
|
$1,760
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs