Assessment Year 1987
Principal Product ARCHITECTURAL PRODUCTS
NAICS
n/a
SIC 3446: Architectural and Ornamental Metal Work
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area
n/a
Annual Production 7,000,000
lb
Production Hrs. Annual 5,760
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $231,934 1,905,920
kWh
Natural Gas $27,796 6,982
MMBtu
Fuel Oil #2 $4,000 896
MMBtu
Fuel Oil #6 $22,600 6,810
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,791 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,791

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $17,912 $12,250 $17,912
147,128
kWh
- -
02 2.2122: Install / repair insulation on condensate lines $219 $132 - $219
-
MMBtu
-
03 2.2511: Insulate bare equipment $1,084 $1,890 - $1,084
-
MMBtu
-
04 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $21,576 $62,000 $27,648
230,363
kWh
$(-3,072.0)
-
MMBtu
$(-3,000.0)
TOTAL RECOMMENDED $40,791 $76,272 $45,560
377,491
kWh
$(-1,769.0)
-
MMBtu
$(-3,000.0)
TOTAL IMPLEMENTED $40,791 $76,272 $45,560
377,491
kWh
$(-1,769.0)
-
MMBtu
$(-3,000.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs