| Assessment Year | 1986 |
|---|---|
| Principal Product | RUBBER CMPDS & PRODUCTS |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
n/a
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $348,987 | 3,699,004 |
kWh
|
$0.094 |
| Natural Gas | $15,606 | 3,252 |
MMBtu
|
$4.80 |
| Fuel Oil #2 | $33,021 | 5,600 |
MMBtu
|
$5.90 |
| Fuel Oil #4 | $30,745 | 5,760 |
MMBtu
|
$5.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,373 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $73,373 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,220 | $200 |
$2,220
23,447
kWh
|
- | - | - | |
| 02 | 2.2113: Repair or replace steam traps | $13,251 | $600 | - |
$6,879
-
MMBtu
|
$6,372
-
MMBtu
|
- | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $34,923 | $1,500 |
$32,289
342,907
kWh
|
$3,234
-
MMBtu
|
- | $(-600.0) | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $9,691 | $720 |
$9,691
102,579
kWh
|
- | - | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $9,992 | $6,740 |
$13,857
146,835
kWh
|
- |
$(-3,865.0)
-
MMBtu
|
- | |
| 06 | 2.1232: Keep boiler tubes clean | $3,296 | $750 | - | - |
$3,296
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $73,373 | $10,510 |
$58,057
615,768
kWh
|
$10,113
-
MMBtu
|
$5,803
-
MMBtu
|
$(-600.0) | ||
| TOTAL IMPLEMENTED | $73,373 | $10,510 |
$58,057
615,768
kWh
|
$10,113
-
MMBtu
|
$5,803
-
MMBtu
|
$(-600.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs