Assessment Year | 1986 |
---|---|
Principal Product | MOLDED RUBBER PRODUCTS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 350,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $511,446 | 6,471,864 |
kWh
|
$0.079 |
Natural Gas | $13,639 | 1,749 |
MMBtu
|
$7.80 |
Fuel Oil #2 | $45,866 | 7,911 |
MMBtu
|
$5.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $188,373 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $178,831 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $4,493 | $3,458 |
$4,493
56,858
kWh
|
- | |
02 | 2.2511: Insulate bare equipment | $13,827 | $2,280 |
$13,827
174,971
kWh
|
- | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $126,986 | $6,650 |
$126,986
1,606,975
kWh
|
- | |
04 | 2.4322: Use or replace with energy efficient substitutes | $27,051 | $2,280 |
$27,051
342,321
kWh
|
- | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,537 | $22,460 |
$8,060
101,993
kWh
|
$(-2,523.0)
-
MMBtu
|
|
06 | 2.4312: Improve lubrication practices | $5,049 | $490 |
$5,049
63,892
kWh
|
- | |
07 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $2,326 | $15,600 | - |
$2,326
-
MMBtu
|
|
08 | 2.2443: Re-use or recycle hot or cold process exhaust air | $3,104 | $6,688 |
$(-208.0)
(-2,638)
kWh
|
$3,312
-
MMBtu
|
|
TOTAL RECOMMENDED | $188,373 | $59,906 |
$185,258
2,344,372
kWh
|
$3,115
-
MMBtu
|
||
TOTAL IMPLEMENTED | $178,831 | $55,958 |
$175,716
2,223,622
kWh
|
$3,115
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs