Assessment Year | 1986 |
---|---|
Principal Product | PROCESSED CHICKEN PARTS |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 4,400,000
lb
|
Production Hrs. Annual | 3,900
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,214 | 516,999 |
kWh
|
$0.091 |
LPG | $6,597 | 671 |
MMBtu
|
$9.83 |
Fuel Oil #2 | $28,605 | 4,339 |
MMBtu
|
$6.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,573 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,347 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $187 | $41 |
$187
2,052
kWh
|
- | - | - | |
02 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $589 | $900 |
$589
6,448
kWh
|
- | - | - | |
03 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $375 | - |
$375
4,103
kWh
|
- | - | - | |
04 | 3.6121: Burn waste paper for heat | $31,590 | $40,000 | - | - |
$18,590
-
MMBtu
|
$13,000 | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $449 | $1,060 |
$803
8,792
kWh
|
$(-354.0)
-
MMBtu
|
- | - | |
06 | 2.2447: Heat water with exhaust heat | $383 | $1,500 | - |
$383
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $33,573 | $43,501 |
$1,954
21,395
kWh
|
$29
-
MMBtu
|
$18,590
-
MMBtu
|
$13,000 | ||
TOTAL IMPLEMENTED | $1,347 | $2,400 |
$964
10,551
kWh
|
$383
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs